Wick Harbour Authority
6/12/2018
Hugh Simpson (Contractors) Ltd. dismantled and removed a lighting tower from Wick Harbour Commercial quay.
The lighting tower was over 30 m high, which required our operatives to work at considerable heights. The tower was cut in 4 sections, each approximately 8-9 m long. Once on the ground each section was downsized to a size suitable for safe transportation.
Ian Cormack, the deputy harbour master, said: ” Contract was carried out efficiently, safely and with minimum effect on other stakeholders. All materials removed from site and made safe within 24 hours.”