Kestrel Liner Agencies Ltd
16/11/2020
Hugh Simpson (Contractors) Ltd unloaded Glen Kyllachy wind farm components at Inverness harbour.
The first of eight vessels MV Aramis arrived at Inverness Harbour on Monday carrying 27 blades each 44 m long and weighing 12.5 Tonnes. Hugh Simpson (Contractors) Ltd was responsible to discharge the blades from the vessel and move them to a storage area on the North Longman storage site. The blades were lifted and stacked 3 high in matched sets to allow removal for a complete turbine at a time.
Read other case studies here.